Hi,

I am trying to reschedule a task with subtasks but it only seems to take the top level task and leave the others

Created by Axel Apr 30, 2018

Hi Axel, When you change the due date of a task, it will not affect this task’s subtasks as each task has its own due date and sometimes, a task is used as an item/category.

Crystal, May 2, 2018

And I think that is the right way to handle it as well. Axel, did you know you can select multiple tasks with the Shift/Ctrl key and set the Date for all of them at once?

Andy, May 2, 2018